MNS-2022-003
Private Hospital — Mansoura
Healthcare · Dakahlia · DEC 2025

| Project code | MNS-2022-003 |
|---|---|
| Client | Medical group |
| Consultant | Healthcare facilities consultant |
| Location | Dakahlia |
| Built area | 22,100 m² |
| Floors | B1+G+5 |
| Our scope | Structure, MEP and medical gases |
| Start | SEP 2022 |
| Handover | DEC 2025 |
| Actual duration | 39 months |
| Value | Undisclosed |
| Structural system | RC frame, flat slabs of varying thickness |
| Foundations | Ø0.80 m piles to 18 m in clay |
The challenge, and how it was solved
Highly compressible clay against a strict settlement tolerance in the operating theatres. Settlement was monitored monthly on 48 columns through the structural phase; the highest reading was 6 mm against a 12 mm allowable.
Images




Milestones
SEP 2022
Mobilisation
APR 2023
Piling complete
NOV 2024
Structure complete
JUN 2025
MEP first fix
DEC 2025
Expected handover