MNS-2021-014
Administrative Tower — Nile Corniche
Administrative · Cairo · NOV 2023

| Project code | MNS-2021-014 |
|---|---|
| Client | Listed real estate company |
| Consultant | International consultancy |
| Location | Cairo |
| Built area | 41,200 m² |
| Floors | G+18 |
| Our scope | Structural works, finishes and MEP |
| Start | MAR 2021 |
| Handover | NOV 2023 |
| Actual duration | 32 months |
| Value | Undisclosed |
| Structural system | Reinforced concrete frame, flat slabs, central shear core |
| Foundations | Ø1.20 m bored piles to 28 m, 1.50 m capping raft |
The challenge, and how it was solved
The site sits 40 m from the Nile bank with groundwater at 2.8 m below ground. The answer was continuous dewatering behind a secant pile wall installed before excavation, and casting the raft in three night pours with concrete temperature held under 32 °C. The largest pour was 1,800 m³ over 14 continuous hours from two batching plants.
Images




Milestones
MAR 2021
Mobilisation
NOV 2021
Foundations complete
OCT 2022
Structure topped out
AUG 2023
Finishes complete
NOV 2023
Handover