MNS-2022-021
Pharmaceutical Plant — Badr City
Industrial · Cairo · SEP 2023

| Project code | MNS-2022-021 |
|---|---|
| Client | Pharmaceutical manufacturer |
| Consultant | Cleanroom specialist consultant |
| Location | Cairo |
| Built area | 18,600 m² |
| Floors | G+2 |
| Our scope | Structure, finishes, cleanrooms and utilities |
| Start | FEB 2022 |
| Handover | SEP 2023 |
| Actual duration | 19 months |
| Value | Undisclosed |
| Structural system | RC frame with beam-and-slab roof, 12 m spans |
| Foundations | 0.80 m raft on calcareous ground |
The challenge, and how it was solved
Grade C and D cleanrooms required floor flatness of 3 mm over 3 m and pre-set levels for 400 mechanical penetrations. The MEP model was built before casting and 312 clashes were resolved in the technical office, so penetrations were formed in the shuttering rather than cut after the pour.
Images




Milestones
FEB 2022
Mobilisation
OCT 2022
Structure complete
MAY 2023
Cleanrooms complete
AUG 2023
Commissioning
SEP 2023
Handover