MNS-2019-011
International School — Shorouk
Education · Cairo · AUG 2020

| Project code | MNS-2019-011 |
|---|---|
| Client | Education group |
| Consultant | Egyptian consultancy |
| Location | Cairo |
| Built area | 14,300 m² |
| Floors | G+3 |
| Our scope | General contracting |
| Start | JUN 2019 |
| Handover | AUG 2020 |
| Actual duration | 14 months |
| Value | Undisclosed |
| Structural system | RC frame, flat slabs |
| Foundations | Isolated footings, bearing 2.0 kg/cm² |
The challenge, and how it was solved
Handover was tied to the start of the academic year, which is a fixed date that does not move. A second finishing shift ran from month nine, and the academic block was handed over three weeks ahead of the sports hall so term could start on time.
Images




Milestones
JUN 2019
Mobilisation
DEC 2019
Structure complete
JUL 2020
Finishes complete
AUG 2020
Handover